How to migrate from Zephyr Squad or Zephyr Essential

Zephyr Squad and Zephyr Essential both export test cases to Excel. They keep tests in different places, and neither export carries your run history. Check which one you have, export the tests, then pick where they go.

Zephyr Squad or Zephyr Essential: check which one you have

In April 2025 SmartBear renamed Zephyr Squad to Zephyr Essential, and Zephyr Scale is now sold as Zephyr. The old Squad listing on the Marketplace carries the new name, and its listing page says Zephyr Essential was previously known as Zephyr Squad. Open one of your tests:

Zephyr Squad
The test is a Jira issue of the Test issue type, with a key like WEB-12. Its steps have three fields: Test Step, Test Data and Test Result. Test Result holds the expected result, not the outcome of a run.
Zephyr Essential, test case library
The test case sits in Zephyr’s own library, outside Jira’s issues, with a key like WEB-T12. Zephyr shows each project in four tabs: Test Cases, Test Cycles, Test Plans and Reports. A test case holds steps (Step, Test Data, Expected Result), a plain-text script or a BDD script. A fresh install on our test site gave us this version in October 2026.

Export test cases from Zephyr Squad to Excel

Use Zephyr’s own export, since Jira’s issue export doesn’t include Squad’s test steps. SmartBear’s export guide gives this path:

  1. Apps
  2. Zephyr Squad
  3. Test Cases
  4. Export Test Cases

Then choose one of two options. If your tests have keys like WEB-T12, use the Zephyr Essential export below.

Export Excel (all fields)
Every test case field. Take this one, so no column you need goes missing.
Export Excel (current fields)
Only the columns shown on the Test Cases page, as set in its Columns menu.

You get an .xlsx workbook. Open it and check that each test’s steps are there.

What the Squad export leaves out

  • BDD tests. Per SmartBear, only non-BDD tests export, so BDD Scenarios and BDD Features stay behind.
  • Run history. The file holds test cases, and their executions stay in Zephyr’s test cycles.
  • Attachments. SmartBear’s export guide doesn’t mention them, so plan to move step attachments by hand. Files attached to the Test issue itself are Jira attachments and stay on the issue.

Export test cases from Zephyr Essential to Excel

Open Zephyr Essential from the Apps menu and pick the project. On the Test Cases tab, tick the test cases you want, then go to

  1. More
  2. Export to Excel

Export to Excel stays greyed out until you tick at least one test case. The same menu has Export to XML, and Export feature files (BDD - Gherkin) for BDD scripts.

The workbook has one row per step. A test case’s fields fill its first row, and each further step follows on a row with an empty Key. Our export from October 2026 had these columns:

Test case
Key, Name, Status, Precondition, Objective, Folder, Priority, Component, Labels, Owner (an Atlassian account ID, not a name) and Estimated Time
Coverage
Coverage (Issues) and Coverage (Pages)
Test script
Test Script (Step-by-Step) - Step, - Test Data and - Expected Result, then Test Script (Plain Text) and Test Script (BDD)

BDD scripts come along as text in their own column. No column holds attachments, executions or test cycles.

Save your run history before you uninstall Zephyr

The test case exports above stop at the tests. SmartBear documents a separate export per test cycle, so run it while Zephyr is still installed, unless you stay on Zephyr.

Zephyr Squad
Per SmartBear’s cycle export page: click the test cycle’s name, click the gear icon on the right, then choose Export Tests. You pick CSV, HTML or XML. Repeat for each cycle you need.
Zephyr Essential
SmartBear’s product comparison says cycles export to Excel from reports. It gives no menu path and we haven’t run this export ourselves. Start on the project’s Reports tab.

SmartBear’s pages don’t list the columns of either file, so we don’t know whether each test’s execution status or its step results come along. Export one small cycle first and open the file. If the results you need aren’t in it, ask SmartBear support before you remove the app.

Where to take your tests

Your options in October 2026, with each vendor’s own description of the move:

Stay on Zephyr Essential
Nothing to export or import, and your run history stays where it is.
Upgrade to SmartBear’s Zephyr
Per SmartBear’s upgrade guide, the upgrade from Squad is in beta, starts with a support ticket and needs a new licence. BDD data and test execution history aren’t migrated yet. SmartBear’s roadmap lists both for Q1 2027, subject to change. Its migration page names more that stays behind: audit logs, saved filters, cascading and label custom fields and advanced test case custom fields. A migration can’t be cancelled or topped up with later changes, and running it again overwrites the first one.
AIO Tests
A test management app for Jira. Its support page describes a utility for importing cases, cycles, folders, plans and execution information from Zephyr, which you request from the AIO team. Its August 2026 post lists executions with their results among what moves. Attachments and evidence get uploaded separately, and it says not to assume comments, audit records or other history come along.
Qase
A separate test management service with a Jira app. Per its Zephyr guide, the in-app import reads test cases, steps and priority from a Zephyr XML export, and API tools you run yourself bring the folder tree, test cycles and executions. Zephyr Essential’s library exports XML. Squad’s test case export is Excel only, so read the guide’s notes on Squad first.
Test Cycles for Jira
Our app, on the Atlassian Marketplace. It adds steps to your Squad Test issues and turns Essential test cases into new Test issues. Run history stays in Zephyr, so save it first. How the import works

Xray, QMetry and TestRail also publish guides for moving from Zephyr. Prices, CI and BDD support and where each app keeps your tests are side by side in Zephyr Squad alternatives compared.

Import into Test Cycles for Jira

Test Cycles for Jira, our app, runs on Atlassian Forge, and steps, cycles and results stay in your Jira site.

Before the first import

Each project needs a Test issue type and the Tests link type, which a Jira admin sets up once. A project that used Zephyr Squad has Squad’s Test issue type already, so only the link type is new. The setup steps are in our guide. Then open

  1. Tests
  2. Import

Load the .xlsx from Zephyr. If the import says it couldn’t find the key or step columns, rename those headers to Issue key, Step, Test Data and Expected Result, then load the file again. A CSV with those four columns works too, and adds steps to Test issues the project already has. If a file still won’t load, send the column names to support@pretzelhands.app.

The dry run

Nothing is saved yet. The dry run counts the tests in the file, the existing tests that get steps and the new Test issues the import will create. Each skipped test shows its reason, such as a key that isn’t in this project or more than 200 steps. Tests that already have steps keep them, unless you choose Replace their steps.

From Zephyr Squad

Each test’s issue key finds its Test issue in the project, and the steps go onto it. No issue is created, and each Test issue keeps its key, links, comments and attachments.

The Tests panel on a test issue: step 2, Fix the card details and pay again, with its test data and expected result, the Add step and Save steps buttons, the story it tests (WEB-1 Guest checkout) and its runs. The run in Release 2.4 regression failed and has bug WEB-14.
The Tests panel on a Test issue, where imported steps land: step 2 with its action, test data and expected result, the story the test covers and its runs.

From Zephyr Essential

Each test case becomes a new Test issue in the project, with

  • its steps, or its plain-text script as one step
  • its objective and precondition in the description, and a BDD script there as text
  • a line in the description naming the Zephyr key and folder, since folders don’t come across as a structure
  • its labels, with spaces turned into underscores, because a Jira label has no spaces
  • Tests links to the Jira issues listed under Coverage (Issues)

WEB-T1 in the Zephyr Essential export

NameGuest pays with a saved card
ObjectiveCheck that a guest can pay with a card saved in the browser
PreconditionShop has a jacket in stock
Folder/Checkout
Labelscheckout
Coverage (Issues)WEB-1
Test Script (Step-by-Step)2 rows of Step, Test Data and Expected Result

Guest pays with a saved card

Check that a guest can pay with a card saved in the browser

PreconditionShop has a jacket in stock

Imported from Zephyr test case WEB-T1, folder /Checkout.

  1. 1Add a jacket to the cart and open checkout as a guest
    Pick the green oneData: Size M, greenExpected: Checkout asks for email and address only
  2. 2Pay with the saved test cardData: 4242 4242 4242 4242Expected: Payment succeeds and the order number shows

checkout

Tests WEB-1 Guest checkout

Test case WEB-T1 from our demo export, and the Test issue the import makes from it. steps in the Tests panellabellink from Coverage (Issues)

Import the same file again and no test case turns into a second issue. Creating the issues takes permission to create and edit issues in the project, and the links take permission to link issues.

What doesn’t come across

Run history
Zephyr’s executions and test cycles. Save them first and plan your next cycle in Test Cycles.
Attachments
Files on Zephyr steps and on Essential test cases. Attach the ones you still need to the Test issue.
Other fields
Status, Priority, Component, Owner, Estimated Time, Coverage (Pages) and custom fields of Essential test cases. A Squad Test issue keeps all its Jira fields.

Free for sites with up to 10 users. Sites with 11 to 100 users pay $1.50 per user per month, less per user on bigger sites. 30‑day free trial.

FAQ

Is Zephyr Squad reaching end of life?
We found no end-of-life date for Zephyr Squad Cloud or Zephyr Essential in SmartBear’s documentation when we last checked in November 2026. Its end-of-support policy for Squad Cloud covers old releases, not the product. SmartBear has run a webinar on migrating from legacy Zephyr Squad Cloud, so ask SmartBear support which date applies to your site.
Do I have to uninstall Zephyr before I import?
No. The import reads the file and changes nothing in Zephyr. Keep both apps installed while your team switches, and save the past results you need before you uninstall Zephyr.
What if an import stops halfway?
Load the same file again. The tests left over go in, and missing Tests links get added. A test case cut off while its issue was being made stays locked for 5 minutes and shows as skipped until then.
Does Test Cycles work with Jira Data Center?
No. Test Cycles is for Jira Cloud.